AQW 12510/22-27 Written question to the Minister of Finance

To ask the Minister of Finance whether developers can begin construction work, at their own risk, before they have been granted plan approval from Building Control.

Asked by Kate Nicholl MLA on 24 May 2024

  • Answered
  • Written
Tabled
24 May 2024
Answer due by
11 June 2024
Answered
10 June 202417 days after tabling
Department
Department of Finance
Priority question
No

Answer

The Building Regulations do not prevent developers from commencing construction work at their own risk prior to their plans being passed by the district Council. Failure to provide notification to the district Council prior to commencement of work or to submit a plans application where required, however, would be a contravention of the Building Regulations.

Official sources