AQW 11512/22-27 Written question to the Minister of Education

To ask the Minister of Education for an update on progress towards the new build project for St. Bride's Primary School, South Belfast.

Asked by Kate Nicholl MLA on 8 May 2024

  • Answered
  • Written
Tabled
8 May 2024
Answer due by
23 May 2024
Answered
16 May 20248 days after tabling
Department
Department of Education
Priority question
No

Answer

St Bride’s Primary School is proceeding in design under the School Enhancement Programme.

The project is at Technical Design stage (RIBA Stage 4), which is the final design stage before construction tender. Planning permission was received from Belfast City Council on 14 May 2024.