AQW 11512/22-27 Written question to the Minister of Education
To ask the Minister of Education for an update on progress towards the new build project for St. Bride's Primary School, South Belfast.
Asked by Kate Nicholl MLA on 8 May 2024
- Answered
- Written
- Tabled
- 8 May 2024
- Answer due by
- 23 May 2024
- Answered
- 16 May 20248 days after tabling
- Department
- Department of Education
- Priority question
- No
Answer
St Bride’s Primary School is proceeding in design under the School Enhancement Programme.
The project is at Technical Design stage (RIBA Stage 4), which is the final design stage before construction tender. Planning permission was received from Belfast City Council on 14 May 2024.