AQW 6136/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure for an update on the development of the proposed North Belfast to South Belfast Glider route.

Asked by Kate Nicholl MLA on 12 February 2024

  • Answered
  • Written
Tabled
12 February 2024
Answer due by
27 February 2024
Answered
22 February 202410 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

I announced the preferred route for BRT2 in October 2022, along the Antrim Road in the north and along the Ormeau Road and Saintfield Road in the south. I decided that the north and south routes should extend to Glengormley and Carryduff, respectively with the feasibility of these extensions being further assessed as part of the detailed design. The announcement also noted that the existing G2 City Centre to Titanic Quarter Glider service will be extended to connect with Queen’s University and the City Hospital.

In line with this decision, work is almost complete to determine the feasibility of extensions to Glengormley and Carryduff, to conclude the Outline Business Case, and recommendations on the way forward.