AQW 19884/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure (i) to detail the number of (a) road; and (b) lane closure approvals that have been issued retrospectively by his Department in the last 12 months; and (ii) to detail the proportion of total approved (a) road; and (b) lane closures within that period that were issued retrospectively.
Asked by Kate Nicholl MLA on 13 December 2024
- Answered
- Written
- Tabled
- 13 December 2024
- Answer due by
- 3 January 2025
- Answered
- 3 January 202521 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
My Department process over 22,000 road restrictions application each year from a range of stakeholders. Article 7 of the Road Traffic Regulation (NI) Order 1997 stipulates that the Department may give authorisation to restrict or prohibit the temporary use of a road by traffic. It is illegal for a road to be obstructed without my Department’s authorisation, with the exception of emergencies, or, for under a 15 minute duration.
In principle, approvals should be sought and approved before an obstruction is put in place on a road. However, there can be a small number of instances when retrospective approvals are granted. Such examples include, a follow-up approval after an urgent verbal request by a stakeholder requiring a restriction to be put in place, or, a late notification seeking an extension to an existing closure.
Since 1 April 2024, my Department has implemented a new online application process that allows such information to be extracted. Regrettably, it has not been practical to undertake a manual check of applications before April 2024 due to the volume of applications held in a manual system. However, I can advise that between 1 April to 16 December there were 15,401 approved applications of which 445 (2.9%) were retrospective approvals. The table below splits these between road and lane closures.
| Closure type | Total number of approvals (1-April to 16 December 2024) | Retrospective approvals | Percentage |
| Lane Closure | 10,980 | 288 | 1.9% |
| Road Closure | 4,421 | 157 | 1.0% |
| Total | 15,401 | 445 | 2.9% |
I would also advise that the enforcement of temporary road restrictions is the responsibility of the PSNI.