AQW 12701/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure what guarantees he can provide that the Belfast Rapid Transit Phase 2 will be fully funded.

Asked by Kate Nicholl MLA on 30 May 2024

  • Answered
  • Written
  • After due date
Tabled
30 May 2024
Answer due by
14 June 2024
Answered
17 June 202418 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

The estimated cost of the North Belfast to South Belfast Glider route is currently in the range of £142m to £148m. £35m of funding has been secured through Belfast Region City Deal.

My Department has been operating in a difficult financial environment for a number of years due to underfunding and austerity by the British Government. The value of our infrastructure cannot be overstated, and I will continue to work with Executive colleagues and the Belfast Region City Deal Partners to ensure that the appropriate level of investment is made available to deliver the project.