AQW 38913/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure to detail any preparatory work being undertaken by her Department regarding Translink's rail expansion plans, including the reopening of the Knockmore Line.

Asked by Kate Nicholl MLA on 23 January 2026

  • Answered
  • Written
Tabled
23 January 2026
Answer due by
9 February 2026
Answered
5 February 202613 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

In 2025, Translink concluded work to undertake the initial development of four projects outlined as a priority in the short-medium term in the All-Island Strategic Rail Review. These were the reopening of the Antrim to Knockmore line, the Portadown to Derry line, the Portadown to Armagh line and Electrification from Belfast to the Border. High level outcomes from the study were published in December 2025 as part of the Shaping the Future document https://www.translink.co.uk/about-translink/media/pressreleases/shaping-the-future

I have allocated £1m in this financial year to progress priority tasks, including detailed technical work on the proposed connection to Belfast International Airport, engagement with planning authorities, development of signalling and electrification proposals, and assessment of user worked crossings along the route.

The delivery timeline for Translink's rail expansion plans including the Knockmore line will be subject to the availability of funding, approval of the necessary business cases, and securing statutory consents.